Our client reimbursed the retailer for $7 million in repair costs and sued the architect/engineer and the electrical subcontractor, who then sued the excavation contractor. After a jury trial to apportion fault among the parties, our client was made whole.
Making our client whole in construction litigation
Our client, an ENR Top 75 construction company, built a data center for a major U.S. retailer that nearly suffered a catastrophic failure due to problems with the primary electrical conduit into the facility.